With the concrete due to be poured late this week, changes to the site this week mainly consist of laying out electrical and plumbing tubing and leveling the gravel around these features.
The footings and the plumbing rough in are complete, and the electrical is nearly complete. Once the concrete is poured these elements are locked in.
The parking lot closest to the site is still closed due to improvements made for better drainage and handicap access. This area will most likely remain closed this week and reopen next week.